Back to search
Emergency Generator Inspection
Quick answer
Every Monday at 07:00, facilities runs a 15-minute load test on Generator A and B, logging fuel level, coolant, and transfer switch status.
Full procedure
- 1Verify fuel tanks are above 75% capacity.
- 2Check coolant and oil levels; top off if below the min line.
- 3Start each generator in manual mode and observe for 15 minutes under load.
- 4Confirm the automatic transfer switch cycles cleanly.
- 5Record readings on Form FAC-88 and file in the Facilities log.
Common mistakes & exceptions
- What if the generator fails to start — Escalate immediately to the Facilities Manager and open a Priority 1 maintenance ticket.
Escalation path & subject matter expert
Escalate to
Facilities Shift Lead
Ext. 4130 · Slack #facilities
Subject matter expert
Priya R. — Facilities
Frequently asked questions
Required forms
- Generator Inspection LogFAC-88
My private notes
Revision history
- 2026-06-30Added ATS cycle verification step.
Was this helpful?
Your feedback improves the knowledge base.